Following the master plan, Patna Metropolitan Area Authority (PMAA) wishes to prepare the ADS. To prepare such ADS, CEPT University, Ahmedabad has been entrusted as the Master Consultant for preparing such ADS vide letter no, PMAA/No. 58/2018-150 dated 02.11.2018, followed by signing of agreement on 17th November 2018.

The scope of work for the said work is mainly divided into 3 stages.

I. First Stage includes the Development of Strategic Implementation Plan. This stage includes preparation of Inception Report, Preliminary Assessment of Patna Master Plan 2031, Delineation of ADS boundaries and preparation of Strategic Implementation Plan. It will include stakeholders’ consultations, regular inputs from the client and site visits. 
II. The stage 2 is Procurement of Consultant’s Service for preparation of ADS. This stage includes tasks like preparation of RFP documents, preparation of TOR for consultants, preparation of Evaluation Criteria, Invitations to bid and conducting pre bid meetings and evaluation of Consultant’s proposal. 
III. The third stage of the project is Project Monitoring which includes Review of Consultant’s deliverables and monitoring of consultant’s work programmes. 

Work DoneWay Ahead
  1. CEPT Research and Development Foundation (CRDF) has been associated as Master Consultant for Preparation of Area Development Scheme(ADS) in PMA.

    Deliverables  from Master Consultants:
    Stage 1: (Development of Strategic Implementation Map)
                  Inception Report (Work Done)
                  Draft Map with Delineation of ADS Boundaries (Work Done)
                  Strategic implementation Plan (In Progress)
    Stage 2: (Procurement of Consultants Services for Preparation of ADS)
                  Draft terms of Reference and Proposal Evaluation Criteria
                  RFP Documents
                  Responses to Pre-bid quarries
                  Bid Evaluation Report
    Stage 3: (Project Monitoring)
    CRDF will deploy a Project Monitoring Team at PMAA offices for monitoring of work carried out by ADS Consultants

  1. ADS within Punpun Area may be developed on priority for Pilot project.
  2. Report on Strategic implementation Plan is likely to be finalized within a week.
  3. Notes on RFPs is under Preparation.